Bunavoneader hydro scheme gets under way

This week sees the contractors starting the civil works at Bunavoneader. The project reached financial closure last week. A joint venture company has now been established for the Trust and its partner, Sustainable Technology Investors Limited to take the project forward.

The 100kW hydro-electric scheme is being built by Duncan MacKay&Sons. The mechanical and electrical works are contracted to Ross-shire Engineering who we started talking to in 2010.


access track week1

The first task is to get an access track in, below the road. This will give access for temporary welfare facilities and the site of the new turbine house. The project will take 9 months to complete due to the long lead time on the mechanical components. We will however be able to complete the civil works in the “dry season” -when it arrives.